Targets of NH Construction

Development and maintenance of National Highways (NHs) is a continuous process. NH projects are identified annually as per available budgetary outlay, inter se priority, requirement of connectivity and traffic density. Government has fixed a target of 11000 Km for construction in the country for the current fiscal year.

Salient features of the models being adopted for construction of National Highways:-

1.Public Funded Projects:  In such types of model, 100% funding is provided by Government. Different types of Public Funded Models are as under:

(i)  Item Rate: Detailed design, specifications & estimates are provided by the employer and contractor is paid for the quantities executed as per item wise rates quoted in the Bid. Cost/Risk of any variation in quantity is borne by the employer.

(ii) Engineering, Procurement and Construction (EPC): In such types of models, full freedom to plan, design and construction is given to the contractor and core requirements of design, construction, operation and maintenance are specified in schedules. Scope for adopting best practices and innovation to optimize the efficiency and economy is available in such types of model. Payments are linked to specified stages of construction. The Contract Price is subject to adjustment on account of variation in the cost and change in scope ordered by employer.

2. Public Private Partnership Projects (PPP):

Different types of PPP Models are as under:-

(i)  BOT (Toll): Private developers/ operators, who invest in toll-able highway projects, are entitled to collect and retain toll revenue for the tenure of the project concession period. Responsibility for design and development of the project is vested with the Concessionaire under this mode. He is also responsible for Operation and Maintenance (O&M) of the project for the entire concession period after it is developed and put to commercial operation. The tolls are prescribed by the authority on per vehicle per km basis for different types of vehicles.

(ii) BOT (Annuity): As in case of BOT (Toll) Projects, responsibility for design, development and O&M of the Project Section for the entire Concession Period is vested with the Concessionaire for the Project. Concessionaire is given Annuity Payments during the O&M period as per provisions of the Concession Agreement. Tolling rights during O&M period vest with the employer after declaration of Commercial Operation of the developed section.

(iii) Hybrid Annuity Model (HAM): Under this model, 40% of the Project Cost is paid by the Government/ Executing Agency as Construction Support/ Grant to the private developer and the balance 60% is to be arranged by the successful bidder during the construction period. The Concessionaire is paid back the amount of 60% along with interest and Operation & Maintenance (O&M) payment in the form of annuities during operation period. While the concessionaire is responsible for the Operation & Maintenance during the concession period. The traffic risk is taken by the project Executing Agency/ Employer. Tolling rights during the O&M period are vested with the employer after declaration of commercial operation of the developed section.

Details of NHs under implementation in the country, as on 31.12.2019 under different models are as below:-

 

S. No Model No. Length

(in km)

Cost

(in Rs. crore)

1 Item Rate 330 5476 24565
2 EPC 929 30594 340722
3 BOT

(Toll)

53 6348 63870
4 BOT

(Annuity)

12 934 16658
5 Hybrid Annuity 116 6388 139766
Total 1440 49740 585582

This information was given by the Union Minister for Road Transport and Highways Shri Nitin Gadkari in a written reply in Lok Sabha today.